Skip to Content
0
Dec 18, 2014 at 11:33 AM

9.1 Resources and scheduling

318 Views

Hi,

9.1 allows you to add Resources to Production Orders. When you add a Resource, B1 assigns capacity quantity either on the Order Due Date or backwards from the Order Due Date (the Automatic setting).

Question 1 - Is there any other ability to schedule Resource? For example, could you schedule it so that the capacity is assigned to 2 days before the Order Due Date?

Question 2 - Is there any concept of a Route so that the use of Machine A is followed by Machine B so that you would see the Capcities used in that date sequence?

Thanks.

Douglas