Project version for Z tables, PS

Former Member
0 Kudos

Dear Gurus,

In a scenario, we have many master data fields which are saved under customer enhancement tables, PROJ and PRPS. But there are many other custom Z transaction tables for WBS element.

We would like to create Project versions same as standard SAP PS. I am not sure if we can create version for custom or Z transaction tables.

Can anyone provide some input in this direction? Are there any custom exits which can be used? or we need to create a TC such as ZCN71 which captures standard and custom Z tables for versioning.

Awaiting for your input.

Thanks in advance.

Regards,

Narender.

Accepted Solutions (1)

Accepted Solutions (1)

sushrut_sheth
Active Participant
0 Kudos

Dear Narendra

Please note that there is no such versioning process for Z tables

you need to build a logic  in developments based upon the dates (posting dates) or created date,

so when ever you create a new data and overlap the previous then instead of overlapping system shall create new value based upon date

next time when you want to display data you can select date (date shall be one parameter in input selection screen)

hope this shall help you out

further beyond this it is better to discuss with your developer(ABAPER)

Former Member
0 Kudos

Dear Sushrut, Thanks for your response. This was the initial solution which we thought earlier but I was looking for standard solution. We are in discussion with ABAP to create Z programs to create the versions.

regards,

Narender.