on 01-26-2017 8:40 PM
Hello experts. This is very important issue, please help
Business case is....
Material is semi- finished product.
Parameters:
- MRP type - V2,
- In-house production: 15 days
- SchedMargin key: Open -30 days, Release - 14 days
MD02 parameters:
Processing key: NETCH
Create purchasing req. 2
Delivery schedules: 3
Create MRP list: 1
Planning mode: 2
Scheduling: 2
Production time as a result from routing is abou 45 min., order quantity is 120
System calculate dates for planned and production orders in the wrong way.
After MD02 the situation with dates looks like below:
1. Planned Order
start: 26.01.2017
finish: 15.02.2017
2. Production Order ( after release of order|)
start: 26.01.2017
finish: 02.03.2017
Why those dates are different? Where could it lie mistake?
I will very appreciate your help, guarantee of reward community points after find solution.
Best regards
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.