Scheduled Report failure - Schedule Inactive

Hi All,

I have issue on Query scheduler. Keeps on Inactive and gets error.

Below is the log file.

My SAP is 9.0 PL12.

Looking for first schedule to be executed before/on 20141212 17:9

Handling schedule

Process timeout; terminating client process

Process timeout; terminated

SAP Business One Client return code:-1

SAP B1 client did not update new scheduyle date and time! Deactivating the schedule to prevent infinite loop.

An error occured while creating report by SAP B1 Client

Schedule processed

Appreciate your help in advance.

Regards,

Harlene

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Dec 12, 2014 at 09:33 AM

    Hi,

    Please refer SAP note:

    1798434 - Report Scheduler Prerequisites

    Thanks & Regards,

    Nagarajan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.