Dear All,
As you can see in my illustration, for some reason I have got a delivery schedule being planned for 30/01/2015. In the material master and schedule agreement, I have not maintained a GR processing time or planned delivery time.
Can you help me understand why MRP is planning the delivery schedule on Friday 30/01/2015 instead of Thursday 05/02/2015 as per planning calendar dates?
Cheers
Hello Evan,
First check the Lot size Setting OMI4, If possible share screen shot .
What is setting maintained against the Scheduling ?
If your Requirement = Delivery date,In that case system consider your requirement date and deliver all material on same day
Ex. 30/01/2015 to 05/02/2015 In that case system deliver on 30/01/2015
Suppose in scheduling maintained like Period end = Delivery date, In that case system consider the period end date and deliver the material
Ex. 30/01/2015 to 05/02/2015 In that case system deliver on 05/02/2015
Please check and confirm the same
Regards
Umesh Mali
Evan,
Can you please show us complete MD04 snap shot and Did you see any exception message for created Receipt element?
BR
KK