Hello everyone.
Please help me. Business processes in the production of my company assumes that the components can be stored not only on the stock production, but also on other stock.
In the manufacturing process we use the standard order type PP01. Customized automatic selection when you release batches of the order. But faced with a problem. If the component is on a different stock, selection of batch for this component is not possible.
How do I configure the availability check that when you release the production order, the system first checks proihvodstvenny warehouse in 2100 and, if not checked finds another warehouse - 2000 and pointed to batch?
Just remove the Production storage location from MM MRP2 view for component or from BOM item details so that system would consider plant stock.
Read below SAP Note Question 1 for more helpful answers 1808922 - FAQ: Components in the production order and process order