activity rate calculation and updation in KP26

Hello Experts

The requirement is that activity rate should be arrived by dividing the actual cost posted to production cost centers with the plan activity entered in KP26.

Further the activity rate should be updated for the next month in variable price field in KP26 against the cost center and activity combination.

Regards

SAP FICO

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 10, 2014 at 03:39 PM

    Hi,

    As per your first requirement the actual cost will divided by the actual confirmed quantity then only actual price will calculates.

    The second requirement you can achieve by running the transaction code KP97, to copay the previous period actual prices to current period plan price.


    Regards,


    Ravi

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 10, 2014 at 05:09 PM

    As Ravi wrote the actual price can be calculated only on both Actual cost and Actual quantities, not something in between.

    Second requirement is making even less sense then the first one, since in KP26 you have planned prices, and the price can have two components: fixed portion and variable portion based on the respective costs used to calculate it. So, the logic of the field is predefined by the system.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 11, 2014 at 06:33 AM

    Hi

    Your first requirement is little confusing. The time frame of both the figures i.e planning and actual posting are different. Activity planning you do at month beginning and actual cost will be posted during the month hence your requirement can not be fulfilled.

    If your intention is that your planned activity rate (say for Dec2014) should be based on the actual expenses of previous month (Nov 2014), this you can do only manually. Take actual expenses figures of Nov, do planning in KP06 with this figure and then do activity output planning in KP26. There is no automatic way of doing so as per my knowledge and other senior fellows here are also confirming the same.

    Second requirement: Copy of price function (KP97 from plan to plan and KP98 from actual to plan) can not change the nature of activity price. It will remain the same as it was in the source. That means if the source activity price is fixed it will be copied as fixed only, you can not influence it. I don't know if any user exit may help you in this.

    Regards

    Rajneesh Saxena

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.