on 12-10-2014 3:39 AM
Hi Experts:
I found the withdrawal quantity is not update in transaction code COOIS . the withdrawal quantity is correct in transaction code CO03. I am looking for some notes .Do you know how to solve this issue ?would you like to give me some advices? thank you very much.
Hi All:
I am very sorry . When I checked my data again . I found there is a default filter on field of final issue in coois .so I saw the withdrawal quantity were Zero. I checked again . the withdrawal quantity is correct . I am so sorry ,thank you everyone .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Liang,
I have one question for you ,
Good issue done with respect to the Production order ?
If possible share your MB51 screen shot or Goods movement document screen shot
And also update your CO03 Screen shot
Regards
Umesh Mali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In COOIS, which list are you selecting? please share screenshots
Thanks,
Prem
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you post goods issue against your reservation, it will show under components screen. If the withdrawal is unplanned (say using MB1A transaction), then it will not show under components screen.
You could choose "Documented goods movement" list under COOIS to get the complete consumption, regardless of whether its posted against reservation or unplanned.
If you still need clarity, go to RESB table and check the details. It will be same as what you see in "Components" under COOIS.
There's another possibility like after TECO of order, you do postings against the order (unplanned as reservations are cleared). This also will not hit RESB and will not show as Qty withdrawn under "components"
Thanks,
Prem
Hi Liang,
If the goods are issued(withdrawn) according to the production order and if some of the goods are issued(withdrawn) as unplanned, both can be seen in COOIS "Documented goods movement" option.
If you want to see the planned goods issue(withdrawn) alone, you can choose Component option in COOIS,
Thanks & Regards,
Hi
If material is consumed for the order as unplanned then it can not get updated in withdraw column of the report. Better you refer documented goods movement tab in the report or MB51 report for the order to get overall material movement and generate the report you want.
Best regards,
Sharat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Could you please share some snaps?Which list you are using. Is it coming in MB51 or not?
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.