Hi experts.

We have a network activity and materials are assigned to that network activity. Now at the time of CN25 the backflushed materials are being consumed in the first confirmation, a parcial confirmation (PCNF). Is it a standard behavior? Why the materials are not consumed on the last confirmation (CNF)?

Best Regards

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello Alessandro,

In OPST , check if Goods Movement indicator is ticked under Logs/Error handling section.

This indicator specifies that if you save a confirmation with goods movement errors (that is, backflushing or automatic goods receipt), then the system displays an error log before saving

The indicator is not evaluated if a process control key has been defined that does not allow the goods movements to be posted online.

Regards

Tushar

didier_bueno
Explorer
0 Kudos

Hello Alessandro:

Check the "Requirement Date for the Component" (Reqmt Date) and the "MRP Distribution Key" (Distribution) fields on the Material Component (General Data Tab).

Best regards,

Didier Bueno

0 Kudos

Hello Didier:

Thanks by your answer.

The function of distribution key is divide up dependent requirements or reservations for this component over time, isn't it? I tried but the distribution key did not solve my issue.

Best Regards