Actual Activity type price is not getting calculated during process order settlement (KO88)

Dear Team,

While run the transaction process order settlement (KO88) actual activity type is not getting calculated for the plant (PP01).

But I am using same costing variant and same Resource for plant (PP02) It's successfully calculated actual activity type price , after run KO88 for Process order.

So Experts let me know any configuration missing for plant related or other conflagration please confirm the same.

Regards,

CO User

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 06, 2014 at 01:06 PM

    KP26 is maintained properly for same cost center

    Regards,

    CO User

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 07, 2014 at 05:59 PM

    Dear Kumar,

    Actually we have maintained same costing variant both the plants but Activity cost is capturing in one plant (PP01)where as missing the same in another plant (PP02).

    Please revert back for solution..

    Regards,

    CO User

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 08, 2014 at 06:22 AM

    Hi Sachin

    None of us is clear on your requirement so far but even then trying to extend you hands. Kindly cooperate with us to give your requirement in detail.

    Apart from the suggestions already given by fellows I would say that to get actual activity prices in production order you need to have actual prices with system and also to go through the revaluation (MFN1) step.

    Even before that please check that you have actual activity prices present with the system.

    Regards

    Rajneesh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.