Chain Carryforward PO

Good morning,

I have a Fund reservation of 1.000 and related to it a Purchase order of 100.

Through FMJ2 I select the carryforward of the PO (value type 51) and its budget associated.

Expected result: I would like the carryforward to take just the 100 related to the PO, 100 from the Fund reservation and of course the 100 for budget.

Budget: +100

Commitments: FR +100 & -100 and PO +100

Result: the problem is that also takes the rest of the fund reservation (900) as commitment and also as budget.

Budget: +100 + 900

Commitments: FR +100 -100 +900 and PO +100

Any idea about how to control this?

regards,

Daniel

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Dec 02, 2014 at 02:52 PM

    This is standard behaviour. If you don't want to carry-forward the rest of reservation, you have to de-commit it.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.