Skip to Content

Inquiry of ECC QA Refresh from Production

Hi All,


My SAP systems landscape involved DEV -> QAS -> PRD and my ECC has integrated with EP, BW, OpenText & others web services configured in T-code: SICF.


I am planning to perform a QA refresh from Production as the data in QA was 2 years ago data. Understand that there are few ways can achieve this QA refresh.


1) Homogeneous System Copy

2) Remote Client Copy

3) Client export from Production and import into QA


I would like to know what is the best practise to perform a QA refresh in situation of dual stack system and integrated with EP, BW & OpenText.


I assumed Option 1 (Homogeneous System Copy) is the highest risk as i am copying the whole PRD DB into QAS system, some integration configuration might still refering to actual PRD EP, BW & OpenText.


What is the best recommendation solutions to perform this QA refresh and least risk of breaking the integration configuration in SAP ECC.


Would appreciate any advise.


Thanks,

Regards,


Thomas.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Dec 01, 2014 at 08:30 AM

    Hi Thomas,

    Options 2 and 3 are only good is you have a small size client and you product client would be used least at the time of refresh. This would be a client refresh.

    The 1st option system copy is the safest and the most reliable in case of your dual stack.

    Since your ECC is connect to BW system, you have 3 strategies for doing it, for which I would suggest you to read notes and guides for your system release which you can find on market place.

    Regards,

    Add a comment
    10|10000 characters needed characters exceeded

    • S Sriram Thomas Tan CheePhong

      Hi Thomas

      When you are perform the Homogeneous system copy method, system export / Import you have to do some of the prerequisite steps

      1. In you source system(On production system) Suspend all the background jobs by using program BTCTRNS1 from release to suspended all the BG jobs (For releasing the BG jobs once you source system export completed by using the program BTCTRNS2)

      2. Lock all transaction user id's

      3. Start the Homogeneous system copy source system export process ..

      4. At your target system, once the import task completed, it will same like at the time of export status (all the BG jobs are suspended & user id are locked)

      You can refer the SAP Note 888210 - NW 7.**: System copy (supplementary note)


      BR

      SS

  • author's profile photo Former Member
    Former Member
    Posted on Dec 01, 2014 at 09:18 AM

    Hi Thomas,

    Option 1 is the best method that i have used. Yes, After refresh you will find all conections pointing to PRD . Hence, after completing refresh you need to first make the number of background work process to Zero in QAS and then change all RFC connection's and point it to QA .

    Regards,

    Pavan Gunda

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.