Hi,
I have a question about the project stock.
Project Stock is consider by MRP as part of available stock in standard SAP.
However, if I look at the MD04, it doesn’t seem the standard SAP take into consideration of project stock during MRP run. Please see following pictures.
A – There is a stock quantity of 115EA, and a maintenance order requirement of 300EA, and a project stock with WBS element of 120EA.
B – After a MRP is run, a planned order is generated with 185 proposal.
Thanks
Tuff
Project stock is dedicated stock for a certain project.
Is your OrdRes for this project, or is it reserving neutral stock?
If SAP would allow to use this stock for a different purpose, then you get in trouble as you cannot finish your project because of material shortage.
further I can see that you have an exception 26, which means excess stock, hence the MRP controller should take action and transfer this stock from project stock to neutral warehouse stock, then you won't get such a big planned order.