Skip to Content

Decision Point is inactive in Item

Dear Experts,

I have an issue while I approve a Decision Point is a particular Phase, the "Decision Point (DP)" is having Inactive Status, Now the "Decision Point(DP)" can not be approved to proceed further with next Phase.

Kindly give me some input where the link has been broken between DP and Phase.

There is no tick mark on the current active DP.

Regards,

Anil Pattanaik

SCN1.JPG (20.2 kB)
scn2.JPG (20.3 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Nov 27, 2014 at 08:50 AM

    Hi Anil,

    Due to some inconsistency (program error), the DP was not set to 'Active' as expected.

    You can revert to previous DP and approve again. Alternatively, if you have too much business functionality behind, create a report to update the 'Active' flag in the table /rpm/decision for relevant DP.

    Regards,

    Abir