on 11-20-2014 12:07 PM
Dear All
Greetings of the day!
Request No.1
I want to change Lot Size - From Lot Size and To Lot Size in Routing.
I do not want to do in CA02.
There are 10k+ routing data which requires this change.
Please tell me how should i do?
Please explain in detail.
Request No. 2
I want to change New Base qty, Setup time, Machine time, Labor time with reference to Material and Group Counter.
I do not want to do in CA02.
There are 50k+ routing data which requires this change.
Please tell me how should i do?
Please explain in detail.
Please help in this matter and I will be very grateful to you.
Regards
Ayush
Message was edited by: Caetano Almeida "URGENT" removed from the title
Hi ,
you can do mass change by cewb transaction for process please refer document
http://scn.sap.com/docs/DOC-54401
if you have any query kindly revert back.
Thanks & Regards
Sandeep Kumar Praharaj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Ayush,
I will prepare a detailed doc on this, if that's helpful.
In your case, you can do as below:
CA85N
Enter the selection criteria (based on material / group /Task list/operation number etc) from 1st tab. Make sure your 10K+ records are selected in this filter.
In 2nd tab, you can see Std value text details (6 entries) at the bottom. These are your activity details.
Say if you have 5 activities and want to change 3 of them, list the activity quantity, unit, click on adopt, activity type name, click adopt check box.
You also want to change Base quantity. So, click on the "More selection criteria". i.e, the tab at the bottom page. In the "Task list - operation/activity", you can find Base Quantity. click on that and enter the new base quantity you want to change.
If you have more criteria, choose all of them.
Click execute
List of materials will be displayed
Choose all, or filter if your criteria was wrong. Click on "Mass Change".
Hope this helps
Thanks,
Prem
Dear Ayush,
You can use CEWB or CA85N for mass changes.
If you do not want change number to process mass changes through CA85N, then first set the same through OP5A.
Thanks,
Prem
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Develop a BDC for CO02 and change accordingly.
No standard functionality.
Regards,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Ayush,,
Please try CEWB traction code for your issue,
With help of the valid BDC you can achieve your requirement, Refer below SAP note for more detail
488765 - Do-it-yourself EWB programming
Thanks & Regards
Umesh Mali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ayush,
If you want to do a mass change in Routing its better you ask Technical to design a BDC as per your requirement.
It would be difficult to update using LSMW, so please update using a BDC.
Tell your technical the way recording needs to be done, she will do the recoring & write a program, that will be an easy task.
Regards
Pratik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.