Skip to Content
avatar image
Former Member

Dynamic Rule at Charateristic Level

Experts,

If I use "Dynamic mod. at Char. Level", and DMR in place. Is there a way that if the nspection plan includes diffrent characteristics,

Char. A should be skipped at every second lot

Char. B should be skipped at every tenth lot

that SAP allows diffrent skip sequence per Char. in one inspection plan, or place the diffrent DMR on Char. Level?

Thanks in advance

Jörg

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Nov 14, 2014 at 05:49 PM

    Hi Joerg,

    The DMR assignment is for individual characteristic. You can you 2 different DMRs in one operation.

    Best Regards,

    Rahul

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 14, 2014 at 04:35 PM

    Hello,

    I found this information from SAP Help:

    " Dynamic modification at characteristic level

    The decision concerning the next inspection stage is made at characteristic level.
    You have two options for assigning a dynamic modification rule:

      • At characteristic level:
        You assign a dynamic modification rule to the characteristics that are to be modified.


      Dynamic modification at characteristic level


        • Dynamic modification at the characteristic level is only possible if the QM inspection data for the material is set for the recording of characteristic results.
        • If the task list calls for dynamic modification at the characteristic level and the material is not set for the recording of characteristic results, no dynamic modification is carried out. The quality level is not updated."

        Regards,

        Natália