Dear SAP Experts,
Please guide me how to create production order of FERT material without maintaining MRP views in Material master. How is it possible? What Configuration is require to do so.
Regards
Muhammad Umar
Hi Muhammad Umar,
In my understanding it is mandatory. There is an option to create the production order without material, but this is not what you are asking.
You could use MRP profile and MRP groups to assign values to each field.. but the views are needed if the material is going to be assigned in the order.
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Umar ,
Without maintaining the MRP Views & workshedulung views you cannot create the Production Orders ,
Can you please specify , your exact business requirement , what your client requires .
Regard's
Tallha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Umar,
Expected this was due to user reluctance. I don't think the screen variant at CO01 will help in this case.
User will have to create the material master.You can ask them to use reference FERT material so that they can simply press enter and proceed, or in worst case provide a BDC or LSMW for mass creation.
Normally it is the responsibility of user to create the material master and they must own the same.
Thanks,
Prem
Hello
I don't think that it's possible. You must create at least the work scheduling tab.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Umar,
Prod order one of master data is Material Master,
In Material master, Some filed are mandatory , Which you have to maintained for creation of the prod order, and MRP view cover in this material master data, Without MRP view maintained not possible to create Prod order
Why you want create the Prod order without MRP view ?
Regards
Umesh Mali
Hi Umar,
As i understand, It is not possible to create order without maintaining MRP views.
If your requirement is something specific user reluctance, you can ask them to copy from a reference FERT material, or create an MRP group and assign the same to Material type FERT.
Still the views have to be maintained.
Thanks.
Prem
Hello
I don't have access to my system right now to test, but this error message is very clear: You have to create the MRP views to be able to create a production order. Some information, such as the MRP controller for example, is only available on the MRP tabs of the material master, therefore, you must create the MRP views.
You may try to create only tab MRP1 and then test the creation of a new production order. If the error comes again, try to create tab MRP2, and so on, in order to find out which tabs are mandatory.
BR
Caetano
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.