on 11-06-2014 5:45 AM
Dear Expert,
I have set MRP type V1 as our MRP procedure (Manual Reorder Planning w/ External Requirement). The following scenario that I am facing problem;
ROP = 100
Lot Size = HB = 110
Stock available = 0
Plan Delivery Time = 45
Planning Horizon = 75 days
Sales Order #1 = 20 (Delivery Date = 15/01/2015)
Sales Order #2 = 100 (Delivery Date = 30/01/2015)
Sales Order #3 = 150 (Delivery Date = 15/05/2015)
When I run MRP on 01.12.2014 with parameters;
Processing Key = NETPL
Create PR = 1
SA Delivery Scheduling line = 3
Create MRP List = 1
Planning Mode = 3
Scheduling = 1
The system trow me result (MD04)
PR = 380 w/ delivery date 15.01,2015 (Plan delivery Time is 45)
My query is, why does the system consider all requirement even beyond Planning horizon, the result suppose to be PR = 230. Is it V1 does not consider Planning horizon and how to rectify? Appreciate any single answer, thanks.
Best regards,
M. Mahjuddin
one figure is missing: your current stock.
how MRP does with V1 reorder point with external requirements is explained with example in OSS note 51576 - MD01: MRP type V1/V2: reorder point w. requirements
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Jurgen,
Thanks for quick response, actually in my scenario I have mentioned the current stock = stock available = 0. Understood, my question is, is true V1 does not consider Planning Horizon and if yes is there any workaround on this issue. Can I use MRP type PD and Lot Size HB, instead of using ROP can I maintain safety stock?
Best regards,
M.Mahjuddin
Dear Caetano,
Understood that the planning horizon is working base on working-day. However, even I run MRP with NETPL system was taking the requirement in one year advance while planning horizon only 75 days. I have gone through the setting of V1, standard SAP only provides " " External requirement are not taken into account, 1. External requirement in total horizon, 2 External requirement within replenish lead time. So my question, is it true planning horizon not considered for V1?
Best regards,
M.Mahjuddin
Hi
I know that posting to old threads is not a good habit (forgive me ) but this question was asked again on the PP forum and I made a lot of research about it.
Basically, reorder point with external requirements will consider external requirements outside the planning horizon, because otherwise a planning run with key NETCH would calculate a different quantity for the replenishment proposal than a planning run with key NETPL, which is not a desired behavior.
Please find the details of my analysis on the thread below:
BR
Caetano
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.