on 11-05-2014 8:17 PM
Hi everyone,
I read that if you create work centers and the activities types and plan them in the KP26, you should get the actual costs of the internal activities when notifying them. However, I don't get the actual costs after notification in CN25. Is it truth that you can get actual costs after notification?
Thanks for your help
Hi,
Actual cost always come in below scenario:
After GRN if material case
Time-sheet confirmation if resource case
work center actual cost once confirm the job or prod. order.
KP26 is the demonstrate of cost calculation which will work based on work center and activity even cost center with appropriate formulas so just in KP26 we put rate for particular activity type.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lisbeth ,
1 Create Activity Type in KL01
2 Maintain Rate in KP26
3 Create Work Center & Assign the Activity type in Work center's Costing Tab
4 Then Assign that work center in your Internal Activity (If you have single activity type the you can assign activity type in activity directly also below work center )
5 Then confirm the activity by CN25 ( Check the activity Type while confirming for reference )
6 Check your Confirmation by T code -CN48N & Check cost by T Code- KSB1 with reference to cost center
Thanks ,
Virendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Follow below steps to get plan and actual cost of internal activity,
1. Crate Activity type in KP26 with rate & UOM
2. assign Activity type & work center to internal activity.
3. Assign work to the internal activity.
4. Now you will get the plan cost of th activity.
5. Confirm the activity by CN25.
6. You will get the actual cost of the activity.
thanks
Dnyanesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lisbeth,
Have you maintained the cost for Work Center Cost Center and Activity type in KP26 combination, with Price should be maintained in Fixed price column in current year 2014.
Then once you confirm the activities in CN25, you can check the network activities whether the status is changed to CNF.
Please attach some screenshot, so it will easy for others to check it.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lisbeth,
It looks like you are confusing notification with confirmation. Please search the forum for CN25.
There are quite a lot of master data involved, but if everything is setup as it should be, you will get actual cost through confirmation.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.