Hello Experts,

We have completed the Configuration for a SAP FI Implementation Project. The client have performed the UAT with few minor changes, which were rectified. We have then started & completed the CUTOVER activities on the Production (Pre-GoLive Activity), where all the TRs have been transported to the Production client successfully. Asset Accounting module too has been successfully implemented & tested.

Now, just before Go-Live initiation, client requires to change the whole Asset Accounting module, wherein all the Asset Classes, are said to be deleted & re-create the whole set of new Asset Classes.

Please suggest what should be done. Whether re-creating the Asset Classes & restructuring the Asset Accounting module again is a feasible solution as of now ? What could be impact of these restructuring on our CUTOVER & GO-Live activities.