Intergration of PM - PS

Former Member
0 Kudos

Respected Experts,

I kindly request all of to help me with the integration of PS & PM.

I am new to PM, so would like to have few documents/ screenshots with tcodes for better understanding & for having hands on experience.

Thanks in Advance,

Moumita Basak

Accepted Solutions (0)

Answers (1)

Answers (1)

MTerence
Active Contributor
0 Kudos

Hi Moumita,

Please go through this link

Google

Regards

Terence

Former Member
0 Kudos

Sir,

Thanks a lot for your prompt reply, but it will be good if I got some documents explaining the process.

Regards,

Moumita Basak

MTerence
Active Contributor
0 Kudos

Hi Moumita,

Please find below link

SAP Library - Maintenance Planning

Assignment of PM/CS Orders to Projects - Maintenance and Service Processing - SAP Library

SAP Library - Plant Maintenance (PM)

PM , PS INTEGRATION - Toolbox for IT Groups

I dont think you will be getting the screenshots. In short if i can explain.

In all Industry, there is a concept called Shutdown maintenance. This will be like a project, so they create project, WBS element, Network and Activities. In that certain WBS element they need maintenance work to be performed.

A Shutdown maintenance order is created and WBS element / Network will be account assigned to work order. So the cost involved in the work order will be settled to WBS element / Network. This is the link between PS and PM.

In work order, WBS element field needs to be filled in additional data tab.

I dont see there is any document to display the process, as this needs a collaboration of two modules.

Regards

Terence