Remaining Order Value not transfer into available budget

Dear Experts ,

In Few WBS , report S_ALR_87013558 and CJ30 showing -ve available budget because of Remaining order value is not transferring into available budget

even i have already run CJEN and CJBN .

kindly suggets .

thanks & regards

shailesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Nov 04, 2014 at 08:00 AM

    Hi Shailesh,

    if you have done reconstruct project data then apply to SAP Note :1534265 then check still negative value is showing in CJ30 and other report.

    Regards,
    Sanjeev

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 04, 2014 at 08:11 AM

    Hi Shailesh,

    Please execute report 12KST1C for WBS element via txn CJE0 to see its definition is correct.

    The remaining order plan is calculated as Plan value - commitments - actuals and it will remain 0 as soon as the sum of commitments and actuals reaches and exceeds the plan value (see note 178837).
    Prior executing both transaction, please execute program RKACOR04.

    Regards, Gordon