Plan Actual reporting displays totals at Network level and not Activity

Former Member
0 Kudos

Hi,

When I create a project manually with Network activities. Add plan and actuals data against the Activities. I can view totals data down to the Network Activity level when running e.g. v Plan/Actual/Variance.

However, projects created automatically via a sales order - the data only breaks down to totals at Network level. Even though the plan and actuals are maintained as per above, at Activity level, these projects when displayed in S_ALR_87013532 only display totals down to Network level.

Any ideas why?

Thanks

Kru

Accepted Solutions (1)

Accepted Solutions (1)

sanjeevc
Active Contributor
0 Kudos

Hi,

Check you network type setting is that network header assign or network activity assign?

because this kind of feature under ceiling of network.

Regards,
Sanjeev

Former Member
0 Kudos

Hi Sanjeev,

Thanks for reply. Network Type: I've checked in config, but can't see field or checkbox relating to header or activity assign.

The network type used is has description: Network from Sales Order.

Where or which field should I be checking...?

Thanks

Kru

Former Member
0 Kudos

Thanks. In OPUV - checkbox for Activity Assigment was not checked.

Answers (1)

Answers (1)

sammar81
Employee
Employee
0 Kudos

Hi Kru,

Not really sure but can you check for the projects created using SO is Network header assigned?? Can you check it?

Regards

Sammar