on 10-28-2014 6:51 PM
Hi,
Do someone knows if its possible to determine hours on the shipping document (J3GH) and on the PBE document (J3G$).
We need to rent and equipment 4 hours to a recipient and the others 3 hours to another recipient.
On the requisition note, its possible to define hours. But, at least with our configuration, is not possible on the shipping or PBE (this two are on days, and because is nor possible for the equipment to be on more that 1 recipient for one day .. we cannot complete our scenario)
We need to control stock.
Thanks,
Diego,
If I understood correctly, you want to create two Shipping documents for same equipments and differents Recipients in same day??
It`s possible, but after you create the second one the system will update location for this equipment.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.