Hi PM Gurus,
I'm hoping someone will know the answer to this question...
Why is there a one day deviation between Completed Date and next Plan Date? As you can see from the screen shot below, some times there is no deviation but sometimes there is. So completed date on line 2 matches plan date +1 year on line 3. This is the desired outcome. But then you'll see on line 4, SAP dropped by one day, from July 7 to July 6. Does anyone know a way to correct this?
Best regards,
Julie
Hi Julie,
I guess, 2016 is a leap year, so 366 days.
Regards
Terence
The completion date comes from the TECO data entered in the order.
Then you probably have 100% Shift Factor settings applied in the maintenance plan scheduling parameters.
So, in the case of the 1st line its probably a leap year as explained above.
In the 2nd line, you subtract 9 from 16 to get the 7th.
PeteA
Thank you Pete and Sebastian for your replys. I think I understand now. It appears the Act. Variance is used in the determination for the next plan date.
And yes, I see the subsequent date shifted by one day b/c 2016 is a leap year.
Thank you so much all for helping me understand this.
Best regards,
Julie
Hello Terence,
I have spent the last two days reading and testing in our sandbox. This is my requirement. Regardless of the plan date, if the completion date is X then I need the next scheduled plan date to be X + one year. In other words, the next plan date is based off completion date not previous plan date.
I set up a single cycle maint plan with time key date. When I complete the order two days early, the next plan date is based off the previous plan date and not the completed date as per our requirement. Any ideas how we can set up the system to behave in this way? I appreciate your help.
Best regards.
Julie
Hello Sebastian,
I have tested exactly with the same settings as you in my maintenance plan 887 but I don't get the same result ! Could there be some configuration setting that is causing this issue? Maybe a SAP note that needs to be applied to our system? Thank you for your help.
Sebastian and Terence,
Thank you for your responses. I did another test Sebastian, this time with the completion requirement ticked and unfortunately it did not give me a different result.
I am going to take your suggestion and contact SAP OSS about the issue.
Thanks again for your help.
Regards,
Julie
Hi all,
I just wanted to circle back and let you know how I resolved this issue.
I determined that to influence the next schedule date on our PMs we had to enter the PM completion date in the Maintenance Plan field during the TECO process. This gave us the next PM date as per our business requirement.
That plus creating single cycle maintenance plans and marking the scheduling indicator as time - key date resolved our issue of having the schedule date adjusted due to leap year.
Thank you all for your help and support in my analysis to resolve this problem for our business partners!
Best regards,
Julie Norman
Add a comment