Reg: scheduling type for MTO scenario

former_member184571
Participant
0 Kudos

Dear experts ,

Need you expertise advice on this.

which scheduling type will be more suitable for MTO process...?

Backward or Forward..?  Could you please share an example  on behavior of both scheduling type in MTO scenario..?

Regards,

daya

Accepted Solutions (1)

Accepted Solutions (1)

kiran_kumar179
Active Contributor
0 Kudos

SAP Daya,

For any business scenario Backward scheduling is Recommended because based on requirement date system proposes start date.

Scheduling Types - Production Orders (PP-SFC) - SAP Library

BR

KK

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

MRP always runs a backward scheduling, considering the requirement date as the basic finish date.

Please take a look on the following document for more details:

BR

Caetano

former_member184571
Participant
0 Kudos

Thank you.

Closing this thread