I created Equipment task list for Equipment = XYZ,

so if I create maintenance order for that equipment "XYZ "that time all the defined operation should copy automatically in the maintenance order's operation tab. .

but it is not happening.

Please suggest if any config or step require for that.

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Oct 12, 2014 at 08:12 AM

    Hi... Rao Sir/ Akhilesh,

    thanks for your inputs ......I did the same process earlier.

    but if you maintain task list for particular equipment then its needs to be copy automatically in the operation tab of maintenance order.

    I did not remember the step ...but it is possible ...

    Pls confirm

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 12, 2014 at 12:57 AM

    Hello Lokesh,


    While creating Maintenance Order on the Equipment which has a Tasklist (created through IA01), you need to go to Task list Selection like shown under.

    You may get a Operations pop-up here to select the desired operations. If you want to select all, then clcik on the All button in that pop-up. All your operations of that Equipment tasklist are populated in the operations Tab.

    KJogeswaraRao


    untitled1.jpg (44.1 kB)
    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 12, 2014 at 05:57 AM

    Hi,

    As per SAP standard system does not automatically assign task lists to manually created orders.

    There is two process for assignment to tasklist in maintenance order.

    1- As explained by Jogeshwara Sir.

    or

    2- There are also user-exits to automatically assign task lists to orders.

    IWO10020: Automatically include task list

    IWO10021: Automatic task list transfer when creating order from notification

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.