Hello,

I have one doubt.

Suppose we are using Strategy '10',we manually created the PIR for 100 and 200 pieces on date 08-10-2014 and 10-10-2014 respectively.Also,we have got a sales order of 50 quantities on 14-08-2014.Now,Suppose we have maintained consumption mode 'only backward' with just planning days as 10 days only.Suppose after running the MRP,we have converted the planned order to production order also posted the goods issue,so the PIR is reduced to 50 now.

And now,if we get another sales order on 22-08-2014,So,what will happen to the remaining PIR of 50 units,means will it get consumed or be just remain like that??

Thanks in advance.