on 10-01-2014 3:34 AM
HI Experts,
WE never used capacity planning modules. We recently upgraded to ECC 6 system. System is giving termination messages in capacity leveling and evaluation codes like CM21, cm22 etc. we tried to copy the standard sets from source client 000. But client copy is giving error messages that sets are damaged and cannot be copied. As these sets are in sap name space we are not able to create in manually. Is there any way to create missing sets.
thanks
Rijil
Hi Rijil,
When you execute CM21, you are running CM25 using the overall profile assigned in your User parameters. Identify which is the overall profile and do this:
Note that in the meantime you can try to user other overall profile.. check CM25.
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.