I have fixed 2weeks (10 days) in planning time fence.
but after generating Schedule lines with MD04, quantities have been changed in the fixed qty period.
why?
thanks.
Alaaeddine.
Hello
Since these notes explain the issue, can you please close the thread?
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hello Caetano,
I like to share with you the result of my analysis: the problem was in release process,
in fact, user has changed the "firm zone"(which has higher priority than time fence) customized in ME32L, but befor that, he has runned the MRP, that's why the problem was created.
Alaaeddine.
Hi Alaaeddine,
The time fence forbids the creation of replenishment orders inside the time fence period, during the MRP execution. Now, if you generate orders manually, you could enter an order inside the horizon.
Can you detail how are you generating schedule lines with MD04?
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.