unexpected result with planning time fence

former_member190992
Participant
0 Kudos

hello all,

I have fixed 2weeks (10 days) in planning time fence.

but after generating Schedule lines with MD04, quantities have been changed in the fixed qty period.

why?

thanks.

Alaaeddine.

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Since these notes explain the issue, can you please close the thread?

BR

Caetano

former_member190992
Participant
0 Kudos

hello Caetano,

I like to share with you the result of my analysis: the problem was in release process,

in fact, user has changed the "firm zone"(which has higher priority than time fence) customized in ME32L, but befor that, he has runned the MRP, that's why the problem was created.

Alaaeddine.

Answers (1)

Answers (1)

marianoc
Active Contributor
0 Kudos


Hi Alaaeddine,


The time fence forbids the creation of replenishment orders inside the time fence period, during the MRP execution. Now, if you generate orders manually, you could enter an order inside the horizon.

Can you detail how are you generating schedule lines with MD04?


Kind Regards,

Mariano

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Please read carefully the following notes, which explain the system standard behavior:

204153 - MRP:scheduling agreement schedule line - problems w/ firming

354164 - Sched.agrmt sched.line:only firmng transmittd qties

BR

Caetano

former_member190992
Participant
0 Kudos

Hi Mariano,

the steps are the following:

- Create SA (ME31L)

- create inbound deliveries (VL31N)

-run MRP (MD41).

(MD04 is just to display several changes)

-> schedule lines are automatically generated in ME38.

Alaaeddine.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Alaaeddine

Please read carefully the suggested notes, as they describe exactly this issue.

BR

Caetano

marianoc
Active Contributor
0 Kudos

Hi Alaeddine,

Please read the notes sent by Caetano and please mark Caetano´s response as the correct answer if your are ok.

If you don't have access to the SAP market share ask your technicall support team, or send me a direct email to my personal email.

Thanks and Regards,

Mariano

former_member190992
Participant
0 Kudos

thank you Mariano and Caetano , I have read the notes and it is ok.