Skip to Content

Stability study strategy (IP11)

Dear SAP,

I am facing a issue while creating the strategy planning for stability study.I wan to create strategy on min basic but the system didn't allowed.As we need testing sample to test the stability study.but in strategy minimum time limit is one day so i am not able to test the complete cycle on same day.So how i can create the strategy so that every 10 min stability sample get created and i can do the cycle testing.

Regards,

Asif

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 29, 2014 at 06:10 PM

    Hi Asif,

    1) While creating strategy maintain 'Strategy Unit' as min. Keep the 'Scheduling Indicator' as 'Time- Key Date'.

    2) In the packages assign the duration which you need for testing.

    Best Regards,

    Rahul

    Add comment
    10|10000 characters needed characters exceeded