Budget of IO

91 Views

Hi Sap Guru's

My order budget not showing properly see as below provided details

1)S_ALR_87013019 - List: Budget/Actual/Commitments

Budget Actual Commitment Assigned Available

3200,000.00 993,724.52 136,837.37 1,130,561.89 2,069,438.11

2) When i see in KO23 for same order the budget showing as below

Budget Current budget Assigned

3200000.00 3200000.00 31,92,0820.89

Why here showing assigned values different in both reports for same order

i thanks full them.