MRP based on PAST consumption

Hello,

I need to configure the MRP for one specific material, this MRP should generate the schedule line based on the PAST CONSUMPTION (for this

specific material, should be based on the last month consumption).


So for example. If last month i bought 500 pc, so next month the mrp should generate demand for 500 again.


How can i set this up ?

What configuration in MRP 1 view do i need to use ?

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Sep 24, 2014 at 04:04 PM

    Marcelo,

    You should use consumption based planning for your scenario.

    Please refer below SAP help link for more help https://help.sap.com/saphelp_erp60_sp/helpdata/en/6f/b441a9a1b011d3a82d0000e82a3c24/frameset.htm

    BR
    KK

    Add a comment
    10|10000 characters needed characters exceeded

    • Hello

      As Kiran mentioned, you should use a consumption based MRP type. If you want to consider past consumption, you should use a forecast based MRP type, such as VV. In this case, it is also necessary to create the forecast view of the material master and run the forecast for this material.

      BR

      Caetano

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.