Hi ,

can anybody let me know what are the settings need to be made to create schedule lines through mrp.

we are transferring the stock to sales depot from manufacturing plants. we use sto scheduling agreements for this.

now we want to generate shcdule lines through mrp. i have created schuling agreement and maintained  demand in depot. i have created source list and given 2 indicator in source list. even after doing theses settings i am not able to create sch lines. system is giving pr only.

please let me know the required settings to get auto schedule lines.

thankyou,

mahesh

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member215620
Active Participant
0 Kudos

Dear mahesh Kumar komatineni,

What error you are getting

There is no specific settings for this

Please check the date

dejoy
Active Contributor
0 Kudos

Hello Mahesh,

Check that Scheduling agreement is MRP relevant and maintained in source list.Also when you run planning, specify 3 schedule lines.