PS x SD - Option "Sales doc. date" not available for Milestone with Network

Hi Gurus,

In performing the integration of the billing plan between PS and SD, when using a milestone directly into a WBS Element, the system displays the "Sales doc. Date" option. But including it below a task with a network this option is not displayed.

Does anyone have any tips?

Thank you,

Márcio

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    Posted on Sep 26, 2014 at 05:45 AM

    Hi Marcio,

    Sales Document date Tick is available to milestone attached to both WBS and Activity.

    You may hide the sales doc date tick in field selection.

    Go in T code OPUC (field selection of network details) - make Sales document date un hide.

    With regards,

    Dnyanesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 23, 2014 at 09:59 PM

    Hi Marcio,

    Milestones are assigned to individual WBS elements or network activities. They are never assigned to Network directly .. Rather it is not possible to assign Milestone to Network...

    Please clarify what do u mean by including it below a task with a network.

    Regards

    Tushar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.