Hi Experts,

I am new to SAP PS.

My Client requirement to level capacity in SAP PS.And one activity can be done by multiple skill set.

So what i have done

  • I had created various skill as work center in SAP PP with corresponding capacity type .

  • Now as client need one activity can be done by various skill so i have spitted activity in activity elements in project and then assigned work center at Activity element .

  • Now when i am doing leveling in CM26 or CM32 it is not leveling the capacity even the capacity is not available.And i cannot understand the concept of dispatch and de allocate in proper maner too.

Am i doing some thing wrong or some configuration is still missing.

Thanks

Suraj Prakash