How to run MRP for same material in diff plant

Dear all,

I have a material Ex: 5678AH-i extended this material in two plants.

For ex:

In plant 1100 buying 5678AH material form vendor.

From 1100 plant material is supplied to 2000 plant

I need to run MRP in both the plants

How to process?Kindly please clarify.

Regards

Rajasekaran

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Sep 20, 2014 at 09:42 AM

    HI,RAJA:

    1.Run MRP for plant2000 to generate the dependent requirements

    2.Run MRP for plant 1100 to generate the planned order for above dependent requirements.

    you can either schedule two MRP job in above sequence or configure a MRP scope in IMG to run the MRP .

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear Yang,

      Could you please tell me,what procurement type should be fixed in plant 1100 & plant 2000.

      Thanks & Regards

      Rajasekaran

  • avatar image
    Former Member
    Sep 20, 2014 at 10:28 AM

    Dear Raja,

    aAs per my understanding you should take procurement type as external procurement for 1100 then make Stock transport order for 2000 plant.

    procurement type for 2000 will be both procurement (X).

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 20, 2014 at 11:08 AM

    Dear Raja,

    Try with these settings in the materials master.

    • At Plant 2000
      • Procurement Type = F
      • Special Procurement Type = (yuo have to create a sepcial procurement type for stock transport orders "U", indicating that the supplying plant is 1100. (*)
      • Lot Size = WB or MB or EX, etc.. (if you use EX, try to use a minimum lot size not too small)
      • Then there are other important fields as (lead time, coverage profile, etc..)..
    • At plant 1100
      • Procurement type = E
      • Spec Procrement type = blank
      • Lot Size = WB or MB or EX, etc.. (if you use EX, try to use a minimum lot size not too small)
      • Then there are other important fields as (lead time, coverage profile, etc..)..

    (*) Check this thread to see how to create a Special Procurement Key to linked your plants:

    Kind Regards,

    Mariano