tentative work and forecast work

Hello everyone,

In CNS41, 2 fields are displayed for work : tentative work and forecast work.

what is the difference between the two, how are they calculated ?

Thank you for your help.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Sep 19, 2014 at 01:39 PM

    JP,

    Tentative work is the total estimate of the work that you have defined for each activity.However Forecast work: Actual work + remaining work. Can you provide us screenshots if you are finding any issues in the calculation of forecast work?

    Regards

    Varun

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      hi Narender,

      I found the following confirmations:

      6310094/0010/0132

      actual (total) = 8

      Remaining (last confirmation) = 0

      final confirmation = no

      6310094/0010/0140

      actual (total) = 68.25

      Remaining (last confirmation) = 0

      final confirmation = yes

      6310094/0030/3541

      no confirmation

      Thanks.

  • avatar image
    Former Member
    Sep 22, 2014 at 07:08 AM

    hi Narender,

    I found the following confirmations:

    6310094/0010/0132

    actual (total) = 8

    Remaining (last confirmation) = 0

    final confirmation = no

    6310094/0010/0140

    actual (total) = 68.25

    Remaining (last confirmation) = 0

    final confirmation = yes

    6310094/0030/3541

    no confirmation

    Thanks.