IMCCP1/3

former_member7439
Participant
0 Kudos

Hello,

We do IM34/IMCCP1/IMCCP3.

1.If the AR is released,the investment program & position id link is removed from AR.Is it that after release of AR ,the above functions do not work, specifically IMCCP3. Or exactly in which scenarios it works correctly IMCCP3.Any guidelines or steps

Thanks in advance

Accepted Solutions (0)

Answers (2)

Answers (2)

gerry_hodgins
Active Participant
0 Kudos

Hello SR

If orders or projects were processed, these can be subject to an
availability control, so that you also have to make sure that the values
of the availability control are adjusted after this report runs.

In the case of projects, the availability control that applies here is one
that checks against the budget and not against released values

(see the settings in the budget profile).

To adjust the availability control, start transaction KO31 or CJBN after processing of this report is
finished.

This is also stated as a message after You have executed IMCCP3 in update mode on Your system (the message will be displayed in a log to rebuild availability control).

Ger

Former Member
0 Kudos

Hello SR,

Please refer following SAP note.

947069 - Availability control if budgets or releases are changed

Also search forum.. There are lot of threads already discussed on this forum.

To start with you can refer below thread.

Regards

Tushar