Sep 19, 2014 at 07:21 AM

Quota arrangement is not splitting requirements correctly through MRP run

1717 Views

Hi Experts,

We are planning to implement Quota arrangement in SAP AFS. For that following settings we have done in our test system.

1. In OMI4 T-code , we enabled the splitting quota option for the lot size : EX ,MB,x1,x3.

2. We enabled quota arrangement usage in MRP2 view of material master.

3. We maintained source list (ME01)for the material type : ROH, HALB ,FERT and also enabled the field use in MRP planning .

4. we maintained quota arrangement using t-code MEQ1.

During MRP run , first we are running MRP for warehouse plant from that STO PR's will get generate for finished materials.

So , IN T-code MEQ1 for finished materials we maintained 60 %- In house production and 40% -external procurement .

In our Current business scenario, at the time of MRP External procurement requirement should generates in current date and for In house production requirement should generates in future.

But splitting of requirements is not happening correctly through MRP.

Please suggest us what are all the settings is required to implement for SAP AFS.

Thanks & Regards,

Bhargavi.