Dear Team ,

Can , you please assist , if can we prevent the UD , if goods issue has not been done .

Client  Scenario ,

They need to activate Batch derivation at Usage Decision ,

This is working fine , But a Pre-requisite is that the GI has to be done before Usage Decision , Then only batch derivation works , Else Batch derivation doesnt work during UD .

Can using any user-exit / enhancement can be stop the usage decision , if Goods Issue has not been done .

So Experts ,

Please assist

Reagrd's

Tallha

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello

You can achieve it throught status in inspection lot. You can change status and define what activities are possible and which ones are prohibited. You can use user status too.

Best regards

Carlos Díaz

kiran_kumar179
Active Contributor
0 Kudos

Tallha,

If you are working with 04 Inspection type then just a thought why don't you control the confirmation and GR for order if GI is not been done so that lot generates once all your posting are done with order?

If you agree with this then check BADI WORKORDER_GOODSMVT.

If you have any other concerns then let us know your scenario completely.

BR
KK

former_member184752
Active Participant
0 Kudos

Hi Kiran ,

As explained ,

My  client is looking for Batch derivation to be activated at Usage decision ,

This can be achieved by doing goods issue , then only batch derivation can be triggered at UD.

Here I want to put a validation if Goods Issue not done then system should stop for Usage decision

Regard's

Tallha .

former_member184752
Active Participant
0 Kudos

Hi Team ,

if this can be achieved from any user exits / enhancements or any work around .

Please assist .

Regard's

Tallha