where to specify source of supply in planning version

how to specify source of supply in planning version In the planning version, you can define for PP/DS whether the system may create a procurement proposal if no valid sources of supply are available.

I want to create procurement proposal without source of supply .where i need to specify in planning version.please help me

Thanks in advance

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 15, 2014 at 05:18 PM

    Hello Virender,

    In the T.Code /SAPAPO/MVM Model and version Management double clicks in the planning version 000 and then on the right side scroll down till PP/DS section. Click on change mode. In the field No Order Without Source of supply choose Order Without Source of supply allowed. Save.

    Thanks, Marius