Activate SLED & Manufacturing date fields in COR6N


Hi Experts,

We are using process orders & confirmations are done using COR6N. The materials are managed in batches & are having variable shelf life due to the nature of business & various markets locations. So we can not enter a fixed shelf life in material masters so that automatic calculation of SLED would happen based upon production date entered during confirmation for the batch produced. In COR6N I can see Date of Manufacturing & SLED both fields are there. But those are inactive & we can not enter that values there. Client need is that those 2 fields should be active & we can enter Date of Manufacturing & SLED in those fields during COR6N for the batch.

How to make those 2 fields active in COR6N ? Kindly provide suggestions.

Regards,

MHP

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Sep 13, 2014 at 05:53 PM

    Manish,

    Refer below SAP help link for better understanding on how Calculate the Best-Before Date in the Process Order Calculating the Best-Before Date in the Process Order - Consumer Products for Food and Beverage Industry (PP-PI-CFB) - S…

    BR
    KK


    Add comment
    10|10000 characters needed characters exceeded

  • Sep 14, 2014 at 11:45 AM

    Hi MHP,

    In case you have activated the Expiration Date Check in OMJ5 for your plant and movement type 101, this is what will happens when you do a confirmation:

    1. If you have maintained the fields Total shelf life and Min.Rem.Shelf life in the material master (plant data / stor 1), then the system will ask to enter the manufacturing date and SLED (Expiration date) will be not editable and will be determined baded on your material master settings.
    2. If you have NOT maintained any of the fields Total shelf life and Min.Rem.Shelf life in the material master (plant data / stor 1), then the system will not ask for the manufacturing date and/or SLED (Expiration date). Both fields will be empty.
    3. If you have maintained the field Min.Rem.Shelf life (only this field and not Total shelf life) in the material master (plant data / stor 1), then the system will ask to enter the SLED (Expiration date) and the Manufacturing date will be not editable.

    If you want to enter both fields, in this case you will need to try with a user exit or BAdI. The code of the user exit or BAdI will need to use the function "POPUP_TO_CONFIRM', this way you will be able to enter your date.

    Kind Regards,

    Mariano

    Add comment
    10|10000 characters needed characters exceeded

    • Hi MHP,

      Try with Exit: SAPLMHD1 (function module exit EXIT_SAPLMHD1_001). You can use this exit to calculate the expiration date.

      Chack also BAdI: VB_SLED_MANAGEMENT, Method MAINTAIN_SLED_PARAMETERS.

      I don't think you can make visible both fields at the same time.. as I mentioned there three possibilities.

      Kind Regards,

      Mariano

  • Sep 15, 2014 at 01:38 AM

    Hi Manish,

    Check the below link...

    Thanks

    Kumar