problem CTM calculation in case of IC groups

Hello all,

We have some problems with the calculation of production plan with CTM for interchangeable products.

Example:

Model A will be replaced by model B on 01/12/2014. Model A has a demand of 200 pcs safter 01/12/2014 and a stock of 500 pcs at the end of the horizon. Model B has a demand of 2000 pcs from 01/12/2014 onwards.

We created an IC group for both products with following characteristics:

     Valid date = 01/12/2014

     Location = Cross-location

     Direction = Full

     Use up strategy = Yes

After we run CTM, we see that 2200 planned orders are created for model B.

The 500 pcs of model A, which are still in stock at the end of the horizon,are not taking into account.

From my point of view, if direction is set on full, also supplies of model A should still be taken into account and only 1700 planned orders should be created for model B.

Kind regards,

David

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 15, 2014 at 05:26 PM

    Hello David,

    Did you check the box Stock is Available and Build Up Safety Stock, tab Supplies in the CTM Profile?

    Thanks, MariusĀ 

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hello Marius,

      Build up safety stock is not enabled because we use safety stock days supply ("Consider Safety Days Supply" in supplies tab).

      Kind regard,

      David