Hi everyone

                  while am calculating std cost estimation for finished goods using t-code ck11n am getting below error

                 cost estimate for material 1801rm1/plant 181h is incorrect

I already search on forum but am not able to find the right one to solve my issue.

i had maintained procurement type E for finshed goods in MRP 2 view.

could you throw some points to solve an issue.

Regards

Raj

daksha_995
Member
0 Kudos

Hi experts,
im also getting same error,
could you please share me the solution.

Accepted Solutions (0)

Answers (2)

Answers (2)

john_kennedy6
Explorer
0 Kudos

I was having a similar issue with a couple of materials in BOMs. I went to CKR1 and looked at "Cost Ests w/o Mat. Mater Ref." in Test Run for the BOM component and found an estimate with an error. I looked at it in "Current Std Cost Estimates" as well and found an entry that did not have the error. Both with the same dates Once I deleted the estimate with the error I was able to complete the costing on the parent items.

Former Member
0 Kudos

Hi

my issue has been solved.

Regards

Raj

t_shiva
Member
0 Kudos

Hi Raju,

While running CK11N sytem through the message No.CK168 and Same issue i am not able to find solution .Could you please share me issue resolution steps.