Late coming day's & Late hours calculation

Dear All,

I want to calculate late coming days and late hours for the particular day.

Requirement:-

The planned shift timings is 9:30 - 18:30. If employee Punch IN is after 10:10 (10:11 onward) then it should mark as late come and late hours should be count from planned start time (09:30)

Time Type 9000 = Late hours

Time Type 9001 = Late come day

1. Suppose 1st day punch In 10:30 then


Time Type 9000 = Late hours will be (9:30 - 10:30 = 1 hours)

Time Type 9001 = Late come day will be 1

1. Suppose 1st day  punch In 10:15 then


Time Type 9000 = Late hours will be (9:30 - 10:15 = 0.75 hours)

Time Type 9001 = Late come day will be 1

Best Regards,

Deepak


Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 12, 2014 at 11:42 AM

    Use the operation SNTB to query the planned working time it will work .

    Regards

    Venkatesh

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 12, 2014 at 10:49 AM


    Hi Deepak,

    Write the below PCR and use PTIP funtion. Apply this PCR just after P2011 function in time schema.

    Regards,

    Sankarsan

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 12, 2014 at 04:50 PM

    Hi Deepak,

    Please go through the below document which gives step by step explanation regarding late coming scenario.

    Late Coming, Early Going and Unauthorized absence

    Let me know if you require any further information on this.

    Thanks and regards,

    Vivek Barnwal

    Add comment