Hi,

We want to block the GR if the material is under test or else is rejected by QC. For this we have select source inspection functionality but the system is not blocking GR for under test material or rejected material. Please confirm what setting are missing. However I have made the following setting:

mm02 ---> 0101 insection type and control key as 0007 (Configration -----Good receipt not allowed for rejection)

qp01 -----> 51 Good receipt model

qi01 ------> Inspection control tab -----> Vendor source inspection----> 0101

------> tick not selected ------------ Source inspection- No GR