on 09-11-2014 11:01 PM
Hi,
Earlier i was getting XML stuck in SCM Inbound ( SMQ2), later i removed the leading zeroes from the Idoc in ECC using WE19 for testing purpose. Now the message is not getting stuck in SMQ2 but I am getting below error.
My vendor number is 1084585 & I have assigned the business partner in /n/sapapo/loc3 also.
Any pointers?
Start of inbound processing: ReplenishmentOrderNotification (ID 0000000004948415) 032(/SCA/BIF_ORDER) TST 20140911165526 (type MessageCreationDateTime) was transferred as local time, interpretation as UTC 022(/SCA/BIF_MI) Partner(s) is(are) not found 011(/SCA/DM_MDL) Party 1084585 is not maintained 085(/SCA/BIF_MI) RecipientParty is invalid 038(/SCA/BIF_MI)
Hi Tejinder,
System considering vendor location as 0001084585 and expecting same business partner 0001084585 that's why XML got failed.
Regards,
Nikhil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
The issue is resolved, earlier i created the BP manually in APO. This time i CIFED it from ECC and it worked as the Identification tab in BP is populated with external reference number automatically.
Thanks,
Tejinder
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Harshad,
In case you have created the Business Partner ( BP ) manually in SCM system, please delete it & create it via CIF from ECC. Before you create it via CIF please ensure Identification tab is enabled on the BP. For the Identification tab to get enabled you can execute transaction BUSP in SCM system with option "All Screens". Once this is done from ECC you need to CIF your Vendor using CFM1 - In this select Vendor and on the option of Create Loc./ BP select "Both". The CIF of BP will ensure external Vendor number is mapped with your business partner and your XML will not fail then.
Thanks,
Tejinder
Hi Guru,
I have already maintained the T- Lane, still the XML failing.
Hi Nikhil,
I tried to re-process the Idoc ( WE19) by removing all leading zeroes from Vendor in all segments of PORDCR1, still getting the same error message.
Any pointers?
Thanks,
Tejinder
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I believe T Lane is missing between ship- to & receiving point, maintain the same n reprocess, it should work..
Regards,
Guru
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.