Skip to Content
0
Sep 11, 2014 at 05:03 PM

Purchase Request (PR) to Purchase Order (PO) days taken

433 Views

Expert,

We are using SAP 9.0 PL4

We need Query for PR to PO days taken

Example

I make Purchase Request on 05/09/14 than make Purchase Quotation on 07/09/14 finally made Purchase Order on 10/09/14 with line item 5

We need report

From PR date to PO date. How many days taken?

My problem is how to join with PR to PO directly because PR to PO not tag directly in between we made Purchase Quotation.

Please advise

Thanks in advance

Mukesh Singh