BAPI to Update total plan and actual costs in CJR2 transaction.


Hi Experts,

Is there any BAPI to Update total plan and actual costs for a WBS element in CJR2 transaction?

I tried BAPI_COSTACTPLN_POSTACTINPUT but its not giving the results which I am looking for.

Thanks & Regards,

Prashantha Tadakanahalli

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Sep 11, 2014 at 10:29 AM

    Can you elaborate for planned codst on :

    its not giving the results which I am looking for.

    Also for actual costs, look at BAPI like BAPI_ACC_PRIMARY_COSTS_POST or BAPI_ACC_ACTIVITY_ALLOC_POST (depends on Cost Element)

    Regards,

    Raymond